Power resumed after a week at Tesla's German plant
Paul Lee
hoondork1977@alphabiz.co.kr | 2024-03-13 03:01:41
Tesla logo. (Photo=Tesla)
[Alpha Biz=(Chicago) Reporter Paul Lee] Power supply resumed in a week at Tesla's German plant, which was blacked out due to a fire at a nearby power transmission tower.
Power supplier Edith said it connected Tesla's plant and logistics center to its power grid at 8:45 p.m. on the 11th (local time) and later recovered electricity.
Tesla's German plant outside Berlin was cut off from electricity shortly after a fire broke out at a nearby power transmission tower at 5:15 a.m. on the 5th.
Tesla had originally expected electricity to come back on the 17th.
Tesla expects vehicle production to normalize step by step. A German plant spokesman told rbb, "It is still difficult to say how long it will take for production to resume completely."
Tesla expects to lose hundreds of billions of won due to the plant shutdown.
[ⓒ AlphaBIZ. 무단전재-재배포 금지]
많이 본 기사
- 1TSMC Dominates Global Foundry Market With Nearly 70% Share as Samsung Falls Further Behind
- 2KFTC Slaps $2.3M Fine on 9 Pork Suppliers for Rigging Bids at E-mart
- 3LG Chem, Lotte Chemical Warn of Possible Force Majeure as Naphtha Supply Disrupted by U.S.–Iran Conflict
- 4Prosecutors Raid Korea Ratings Data Over Alleged Credit Rating Manipulation for Bribes
- 5Airfare Surges as Fuel Surcharges Triple Amid U.S.-Iran Conflict; Record Monthly Hike Stuns Market
- 6Retailers Brace for BTS Comeback Concert Crowd in Seoul